start to feed into the Crusher. step 1: When the output temperature Powdering over 90 0 c, launch group outside the 5F1. G14/G01. The devices in the group that runs the following sequence:-Run the 5F1 dust filter. BF02-Run the 5F1 lift bucket. BE01-Run trough the 5F1 vibration. VC015F1 conveyor transfer. BC02 about single mode to easily adjust during operation. step 2: Running the main engines 5F1 Crusher. G04/G01 step 3: based on the temperature and pressure to run the 5F1 Crusher feed system. G01/G02. The order runs the devices in the Group:-Run the rotary valve feed 5F1. RF01-Run the 5F1 dust filter. BF01-Run the 5F1 conveyor. BC01