Today October 11, 2016 according to the progress we have signed today is we have to complete some of the following issues:
1. Retaining wall from 14 ~ 21 (Part pile up for paid software.
2. Complete the double box culvert sections (Part piles and structural parts).
3. The Open Ditch w2000 Complete structural and paid up (From W2000. 19 ~ W2000.35).
4. A single box culvert Route C (start checking time 1).
5. The open ditches W6000 (W2-21) (start test 1).
6. The wall CRW6 and CRW8 (Start test 1).
7. the filling sand (Continue completing the remaining records).
I want to remind you about the progress of our master. Suggest you combine with us soon completed in accordance with its objectives.