Follow the instructions of the Prime Minister in writing number 04/TTg-KTN on 14/01/2015 allows specified for bid form to apply for the remaining work of the package of energy Routes, VSH was quick to deploy, has achieved the following results: a) editing of project construction:-Investment projects construction edit has been consulting joint stock company building power 3 (PECC3), the Power Engineering Consulting joint stock company 1 (PECC1), VSH appraisal in accordance with the current rules.-Industry has reviewed and comments on correction facility design in the text of 6999/BCT-TCNL on 13/7/2015.-The Board of the VSH were approved in decision No. 999/QD-VSH-HĐQTngày 22/6/2015.b) contractor selection results:-Package of 5 km in the first CNN and construction of the tunnel: BOD approves the results was assigned tender, had completed the work to negotiate and sign contracts with the contractor. The contractor began construction in July, 2015, up to now has been the md 470 tunnel.