Except for cases of force majeure as defined in Section 26 DKC, if the contractor does not perform a part or the entire contents of the work under the contract within the time limit specified in the contract, the investor may be deducted from the price contracts a compensation corresponding to the value of the delayed% implemented as stipulated in Can Tho general calculated for each week delay implementation or other time period as agreed until the contents of the work that is done. Investors will come% maximum deduction as prescribed in Can Tho general. When it reaches the maximum level, the investor may consider termination of the contract in accordance with the provisions of Section 29 DKC.