According Dispatch NH91-1 / 551 dated 03.23.2015 of the Consortium Corporation Dat Phuong and Beton 6 Corporation Submitting Reports on environmental monitoring May 1/2015 - Package NH91-1 and Content attached report, we agree with the contents of the report, however, require the contractor to note the implementation of the following:
- Implement monitoring and submission of report results to promptly schedule assess the quality of the environment as well as the proposed control measures.
- Based on the monitoring results, the Contractor shall implement measures to control and pollution control, especially for the monitoring location beyond permissible limits. Strengthening the moistening, cleaning up the site and spheres; speed control and shielding the transport service of the construction project.
- Collect the entire land and moved to the location of waste disposal, absolutely not dump any waste to waste any water source .
The above are some of the content of the request seriously contractors perform.