• Step 1: Install the beam all: after installation, and bearing a stone in place, use the bracket system can be moved horizontally on rails to put into place all the girder design and adjustment determine the position setpoint.
• Step 2: Install the horizontal beam: optical used to anchor the formwork construction system supporting the horizontal beams. Use floating crane put into place beam design, conduct associated with the beam horizontal beam home with wet joints.
• Step 3: Apply deck: assembling prefabricated formwork, construction of reinforced version sphere, carried out concreting the design thickness
• Step 4: Construction of the concrete railing and Asphalt layers: link foot railing with concrete deck with wet joints. Asphalt concrete coat thickness design.
• Step 5: Install expansion joints for structural rhythm: expansion joints fitted with size and position in the design. Complete construction of structural rhythm.