6) Complaints, disputes and arbitration
Not applicable Dispute Settlement Board.
Accordingly, whenever a dispute arises between the parties relating to or arising from the contract or construction contract works , including any dispute regarding the certification, identification, guidance, opinion or assessment of the consultation, either party may propose in writing the Mediation to the other party dispute , have sent a copy to the Consultant. Within 56 days after receipt of this opinion, or within such other time period agreed between the parties, the parties to try to resolve disputes through mediation before lawsuits. However, unless the parties agree otherwise, the arbitration can be conducted on or after the date the notice is not satisfied and intends to sue is made, there is not even an attempt mediation .
arbitration for arbitration procedure is conducted in accordance with the law in Vietnam.
It will be adjudicated people's Court of Hanoi.
The language is Vietnamese referees.
The referees will have full the right to review, revise any certificate, identification, guidance, comments or reviews related to consultant dispute. What will not impede the consultant and representatives of the Parties is called to testify and give evidence before the arbitrators on any matter relating to the dispute.
It would neither party is limited in brought before the arbitrator evidence or arguments previously or unsatisfactory reasons outlined in the notice are not satisfied.
the arbitration may be commenced before or after completion of works. The responsibilities of the Parties, the consultant will not be changed by any reason caused by the arbitration is taking place in the implementation process.
7) Contract Documents
Contract Documents including :
- Number of English original: 5 sets (investor: 2 sets; contractors: 3 sets).
- the number of Vietnamese original: 5 sets (investor: 2 sets; contractors: 3 sets) .
- Number of copies English: 6 full sets (contractor); 6 full set, 4 book contract, 4 books priced BOQ (Investor).
- The number of copies Vietnamese: 6 full sets (contractor); 6 full set, 4 book contract, 4 books priced BOQ (Investor).
The bids of the contractors must be translated into English and the translation section of the construction methods proposed technical dossier of contractors must be notarized translation by state agencies competent.
the entire cost of this issue will be paid by the contractor.
8) Insurance of construction all risks and liability for third parties
- the maximum deduction for hedging of owner: 200,000,000 VND
- limit values liability insurance third party: 50 billion VND.
the two parties agreed on terms of reference as additives insurance Contents 2. Accordingly, the contractors take at least 3 quotations from 3 different insurers and recommended the selection of insurance for investor review and approval.
V. PRICE CONTRACT
Contract Value agreement: VND 516 404 120 088 (in words: Five hundred and sixteen billion, four hundred and four million, one hundred and twenty thousand, eight hundred and eighty-co).
In particular:
- The building Construction and equipment: VND 405 082 657 187 (in words: four hundred and five billion, two hundred and eighty million, six hundred and fifty-seven thousand, one hundred and eighty seven co)
- Paragraph provisional details: 538 361 075 VND (in words: five hundred and thirty eight million, three hundred and sixty-one thousand, five hundred and seventy-dong)
- Paragraph provisional prevention: 63,837,272,727 VND (in words: sixty three billion, eight hundred and three twenty-seven million, two hundred and seventy-two thousand, seven hundred and twenty-seven copper)
- VAT: 46,945,829,099 (in words: forty-six billion, nine hundred and forty-five million, eight hundred and twenty nine thousand, not hundred ninety-nine copper).
V. CONCLUSION
The Contractor shall prepare and complete records BOQ under negotiation and included as part of the contract.
The minutes of the meeting shall be made in 06 Vietnamese and 06 original English original. Each party holds 03 Vietnamese and 03 in English.
In case of any discrepancy, the English version will be the original. BEHALF OF INVESTOR Nguyen Quoc Trung BEHALF OF CONTRACTOR Tran Dang Tu
đang được dịch, vui lòng đợi..