Up to this point, the Contractor has received a total of 2043m / 6418m for both package. However, the fact that the premises were handed over intermittent, not continuous, and many locations are still being disputed, people do not or can not accessible works. On the other hand, the scope of the clearance of the project is handed over is not enough (under pavement width) under the project boundary to the contractor can progress under the profile design. In this regard, the contractor has to report in writing to You agencies (Document No. 019 / Steering Committee-CW3A / 4A dated 12.13.2014, No. 048 / Steering Committee-CW3A / 4A dated 24/03/2015) also provides some solutions to overcome the shortage of space above (Document No. 054 / Steering Committee-CW3A / 4A dated 27.03.2015).