1.9. Technical Instructions (technical explanation) is the norm, the technical standards stipulated for the project and any amendments or supplements to the norms and standards such techniques.
1.10. Design drawings are all drawing, spreadsheet calculations and similar technical information of the works by the Employer to the Contractor and the Owner has been approved.
1:11. BOQ is: a detailed list of the volume and price of work in the contract.
1:12. Parties are: Owner or Contractor depending on specific circumstances.
1:13. Commencement date is: day notice under Clause 7.2 [Time and progress contract].
1:14. Date: to be understood as a calendar day and month calendar month is meant to be.
1:15. Acceptance Report are: the record was released under Article 6 [Ask about product quality and acceptance, handing over the construction contract].
1:16. Contractor's Equipment: all equipment, machinery, vehicles, cars and vehicles, other equipment required to contractors, completion of works and fix any errors ( if any).
1:17. Force majeure is defined in Article 17 [Risk and force majeure]
1:18. Public schools are: investor location over to the contractor for construction works as well as any other location specified in the contract.
1:19. Change is: change (adjust) the scope of work, technical instructions, drawings, contract price or construction schedule when it is approved in writing by the Client.
1.20. Law is the entire legal system of the Republic of socialist Vietnam.
đang được dịch, vui lòng đợi..