9. in case the electrical system operators and power market found the level of prevention, lower power backup backup levels approved the provisions of article 92 of this circular, the electrical system operators and the mobile market can reject the plan maintenance, repair of units and transmission and generator units.10. in case the electrical system operators and market power refuses to plan maintenance, equipment repair, the unit affected has the right to suggest power systems operators and electricity market the plan amendments within a period of seven (7) days.11. power system operators and market electricity must maintain updates on reviews medium-term system security. If the level of prevention, backup power and local power supply security is met, the electrical system operators and market power have to approve the plan of maintenance, repair and modification. 12. after the security system conditions to be met in the medium term, the electricity system operators and market power to publish the entire security evaluation system.