7.2 Party affected by the force majeure event leading to the inability or inability to comply with the contract agreement within 10 (ten) working days from the date of the event of force majeure written notice to the other party. Both parties to the agreement may be affected by a force majeure event be entitled to delay, prolong the fulfillment of obligations in a reasonable time or other suitable measures actual situation at that time .