Demand for water for construction work, living at the site is not large (about 100 m3 / day) can be taken from the canals in the area surrounding the project is put on the reserve tank to be used for implementation drain. Particularly for drinking water will be treated before use.
Freshwater served at sea turbine foundation construction was transported from the mainland and is stored in the water tank located on the barge construction.