Moisture content control when the dress:
The contractor must obtain a sufficient number of samples (not less than 5) in the area before leveling dress material to test the water content. These samples were taken at different locations, from the water content is determined we went determine appropriate density for the embankment.
When the experiments conducted in the laboratory, the samples to determine the amount of water placed in moisture-proof containers such as bottles, glass jars sealed.
the experimental results obtained will be presented to the investor together with the browser section finished up compaction work.
to control soil moisture dress: Sprinklers shower nozzle or watering car but must be directed upwards to create a rain showerhead if the natural humidity is low, if the humidity is greater than the best, you need to spread to dry land leveling until reaching the best humidity conducting new dress. The handling of watering to perform outside the area covered.