In option 1: As accelerate the pouring of concrete beams supporting the stadium seats. The cost is $ 20,000, and cuts construction time items was 6 weeks.
- With a probability of 50%: That is when no matter what happens, the project remains on schedule costs of Option 1 is $ 20,000.
- With a probability of 35% (8 weeks of strike) project remains on schedule and not be penalized for the delay.
+ cost management supplement: $ 500 * 2 weeks = $ 1,000.
that is the total cost in determining productivity 0:35 is: $ 20,000 + $ 1,000 = $ 21,000
-With probability of 15% (12 weeks on strike) project delays take 2 weeks.
+ Cost management supplement is: $ 3,000
+ Do slowed takes 2 weeks against the regulations should be fined loss: $ 15,000 * 2 = $ 30,000.