As per the aforementioned letter, the Contractor Daelim has requested  dịch - As per the aforementioned letter, the Contractor Daelim has requested  Anh làm thế nào để nói

As per the aforementioned letter, t

As per the aforementioned letter, the Contractor Daelim has requested subcontractor BRE17 to speed up work program for construction drawing designing and complete this item on the end of October 2015. However, the designing subcontractor – Britec withdrew from the Project, Bridge Enterprise 17 tried to find a new designing subcontractor and sign the contract to expedite work program, the designing work will cost nearly twice as much as the original designing cost. Bridge Enterprise 17 will try to meet the work program of designing as required by Contractor Daelim and finish it on the end of October 2015. Nevertheless, with some difficult items and site plan have not been cleared such as 2nd Ring Road Bridge, Nhue Bridge, we would like to delay the completion these items until December 2015 (Please see the attached work program for construction drawing submission).
In fact, the work program of design made basis of the non-existent interface problem with other packages and failures of technical design that both the Contractor Daelim and the Subcontractor BRE17 are not able to dispose it. Thus, the work program can be able to adjust according to the unity of the all parties.
We respectfully propose Contractor Daelim to consider and approve this work program for construction drawing design.
0/5000
Từ: -
Sang: -
Kết quả (Anh) 1: [Sao chép]
Sao chép!
As per the aforementioned letter, the Contractor Daelim has requested subcontractor BRE17 to speed up work program for construction drawing designing and complete this item on the end of October 2015. However, the designing subcontractor-Britec withdrew from the Project, the Bridge Enterprise 17 tried to find a new designing subcontractor and sign the contract to expedite work program, the designing work will cost nearly twice as much as the original designing cost. Bridge Enterprise 17 will try to meet the work program of designing as required by Contractor Daelim and finish it on the end of October 2015. Nevertheless, with some difficult items and site plan have not been cleared such as 2nd Ring Road Bridge, Nhue Bridge, we would like to delay the completion of these items until December 2015 (Please see the attached work program for construction drawing submission).In fact, the work program of design made basis of the non-existent interface problem with other packages and failures of technical design that both the Contractor and the Subcontractor Daelim BRE17 are not able to dispose it. Thus, the work program can be able to adjust according to the unity of the all parties.We respectfully propose Daelim Contractor to consider and approve this work program for construction drawing design.
đang được dịch, vui lòng đợi..
Kết quả (Anh) 2:[Sao chép]
Sao chép!
As per the aforementioned letter, the Contractor Daelim has cầu subcontractor to speed up work BRE17 program for construction drawing designing and complete this item on the end of October 2015. Tuy nhiên, the designing subcontractor - Britec withdrew from the Project, Bridge Enterprise 17 tried to find a new subcontractor and sign the contract designing to Expedite work program, the designing work will cost twice as much as the Nearly designing original cost. Bridge Enterprise 17 will try to meet the work program of designing as required by Contractor Daelim and finish it on the end of October 2015. Nevertheless, with some items and site plan khó have cleared được Ring Road Bridge như 2nd, Nhuế Bridge, We would like to delay the purchase until December 2015 completion những items (Please see the attached drawing for construction work submission program).
In fact, the work program of design made ​​non-existent basis of the problem with other interface and Failures of technical design packages mà cả the Contractor and the Subcontractor BRE17 Daelim are not thể dispose it. Thì, the work program can thể adjust theo unity of the all parties.
We respectfully Propose and approve Contractor Daelim như to this work program for construction drawing design.
đang được dịch, vui lòng đợi..
 
Các ngôn ngữ khác
Hỗ trợ công cụ dịch thuật: Albania, Amharic, Anh, Armenia, Azerbaijan, Ba Lan, Ba Tư, Bantu, Basque, Belarus, Bengal, Bosnia, Bulgaria, Bồ Đào Nha, Catalan, Cebuano, Chichewa, Corsi, Creole (Haiti), Croatia, Do Thái, Estonia, Filipino, Frisia, Gael Scotland, Galicia, George, Gujarat, Hausa, Hawaii, Hindi, Hmong, Hungary, Hy Lạp, Hà Lan, Hà Lan (Nam Phi), Hàn, Iceland, Igbo, Ireland, Java, Kannada, Kazakh, Khmer, Kinyarwanda, Klingon, Kurd, Kyrgyz, Latinh, Latvia, Litva, Luxembourg, Lào, Macedonia, Malagasy, Malayalam, Malta, Maori, Marathi, Myanmar, Mã Lai, Mông Cổ, Na Uy, Nepal, Nga, Nhật, Odia (Oriya), Pashto, Pháp, Phát hiện ngôn ngữ, Phần Lan, Punjab, Quốc tế ngữ, Rumani, Samoa, Serbia, Sesotho, Shona, Sindhi, Sinhala, Slovak, Slovenia, Somali, Sunda, Swahili, Séc, Tajik, Tamil, Tatar, Telugu, Thái, Thổ Nhĩ Kỳ, Thụy Điển, Tiếng Indonesia, Tiếng Ý, Trung, Trung (Phồn thể), Turkmen, Tây Ban Nha, Ukraina, Urdu, Uyghur, Uzbek, Việt, Xứ Wales, Yiddish, Yoruba, Zulu, Đan Mạch, Đức, Ả Rập, dịch ngôn ngữ.

Copyright ©2024 I Love Translation. All reserved.

E-mail: