Full payment to Party B on time and to the value of goods delivered as specified in Article 2.
To appoint staff responsible forwarding check and sign documents timely delivery of goods in accordance No. quantity and quality of practice.
Notice about specific construction projects such as: the progress and status of the roads to work for Party B, to proactive delivery to Party A.
Organization promptly unloaded Party B's truck to delivery. If slower than 02 days after the delivery to site B, Party A shall bear the costs incurred by saving the car.
If Party A does not receive the goods were right about the quantity and quality specified under way in the ticket purchase agreement 2% of the value of goods for the first 10 days of delay, penalty of 5% for each period of 10 days. Total fines not exceeding 10% of the contract has been completed.
4. 2 Responsibilities of Party B
Supply construction steel to the site to Party A on time, right quantity, right quality and types required by Party A. In case party B does not deliver on time specified in this contract, Party A to Party B pay fines of 0.5% of goods value for each day of delay. Total fines not exceeding 10% of the contract value.
Party B will provide Party A stock check product quality on delivery and invoice before payment Party A.
If the B deliveries, quality, commodity specifications stipulated in the contract, Party A has the right to reject the goods. Party B must deliver another shipment under strict quality and specifications stipulated, if this barter delay caused damages to Party A, Party B shall bear the cost of damages to Party A.
Party B may stop supplier in case Party A fails to comply with the payment terms specified in Article 2.