Article 47. The order for the test to put into operation the equipment after the connection point
1. During the test to put into operation the equipment after the connection point with the needs of customers connected, the power transmission unit and operating unit power system and electricity market and match customer needs bachelor connected to the operator, competent staff is available 24 / 24h and notify the list of officers directly attached telephone number, fax number to contact the moderate level when necessary.
2. Closing time electrical commissioning and acceptance comply with current operating procedures for the equipment.
3. During the trial operation, customer demand responsibility connected with close coordination with the power transmission unit and operating unit power system and electricity market in order to minimize the impact of the new equipment acceptance testing is to safely operate other devices and power quality of the power system.
4. End process commissioning and acceptance, customer connection needs to confirm actual specifications of electrical equipment, transmission lines, substations and electricity generators. In case of client devices need not meet ONU technical standards in Connection agreement, power transmission unit has the right not to connect the plant or grid customers wishing auction connection to the electricity transmission system and requirements to conduct remedial measures.
5. Grid, power plants and electrical equipment after the connection points of customer demand allowed ONU officially put into operation after full commissioning test records partial and full.