Estimated construction and installation of communications equipment in a train station by a group of construction will include construction groups. Construction time for equipment installation is expected to be 40 days in which the installation time is 20 days, including inspection and test internal signal in the station.
The equipment was installed last day will be handed over to the guard at the site to avoid losing or damaging outsiders.