For other types of machinery, construction equipment does not move to the work you will need to have the vehicle transported to, then the energy in the process of transporting machines and equipment will be calculated as the calculations for the transport of building materials.For example: • Transportation of 100 tons of cement from cement production plant in Spring City (Thanh-Thanh Liem-HA Nam Conference) to construction home condominiums D1-CT2 urban Linh Dam Lake with the shipping distance is 43 miles by truck type 15 tons, the energy in the process of shipping will be : Q = 100 x 70 = 7,000 (Tấn.km) = 7000 x 1.5 = 10,500 (MJ) Convert energy charge according to the decimated transport: 1 Tấn.km = 1.5 MJ• Transport 100000 brick factories two holes from the factory produced bricks of Long Thanh Hai co., Ltd. (Ward PHA Lai-Chi Linh town) came to the construction site of the House condominiums D1-CT2 urban Linh Dam Lake with the shipping distance is 66 km by truck 15 ton, then the energy in the process of shipping will be :