In the contract, HICC and MSC have raised and insisted on the terms and provisions of breach of contract as well as contract termination must clearly state the amount of compensation for the unilateral termination of the contract damage for the parties. Moreover, if a party wishes to terminate the contract, should notice three days in order to avoid damage to the product as well as capital. In the case of MSC then stripped HICC their subcontractors by taking the employee name tag without notice and do not pay for labor and materials for the MSC. Therefore, HICC broke the contract in this case and MSC just based on this provision, and calculate how much compensation that will be paid for their HICC.