9. The changes related to the connection points must be updated in the record of the connection points.
10. Customers using the transmission grid are responsible for storing the data on the working mode, operation, maintenance, maintenance and breakdown on major elements of the scope of their management behind point ONU within five (05) years. When the power transmission unit requests, customers use the transmission grid are responsible for providing a full range of necessary information related to the incident that occurred on the element under its management behind connection points.