Based on the record date of the Contractor on 23.10.2014 difficulties's compensation package CW4A ground, after writing the above investor has solved problems related to ground and was handed over to contractors to implement construction works in the field, the contractor undertook construction Km 18 + 100 words -: - km 18 + 200.
However, in the process of deploying next sections constructed from the base
Km 18 + 200 -: - Km18 + 380 Contractor encountered a stop of some households because they have not received compensation, the contractor has conducted field make a record with the Employer representative as the basis for the resolution of the latter (with minutes attached).