Total fines not exceeding 12% of the contract value. If the time delay corresponding to 12% fines value of the contract or time delayed more than 45 days in a row that the contractor does not have the ability to fix the schedule and there is no logical reason, in addition to contractors must be pre penalties, investors recover all the remaining advance and unilaterally terminate the contract.