Article 16. Compensation for damages for breach of contract
Except in cases of force majeure as defined in Article 18 hereof, if the contractor does not carry out part or all of the contents of the contract within the time limit specified in contract, investors can deduct contract price an amount of compensation corresponding to the value of the delayed% done as prescribed in Can Tho general for each week delay implementation or other time period as agreed content agreement until the job is done. Investors will be withheld until% maximum as specified in Can Tho general. When you reach the maximum level, investors may consider termination of the contract as stipulated in Article 17 of this Chapter.