4.2.2. Steps laying laminate flooring
• Step 1: Installation of floor lining:
- wood floor primer using 2-3mm thick form effective against moisture for wooden floors and limiting noise caused by wood flooring during use.
- When experiencing pads using adhesive tape to stick between the pads together.
• Step 2: Installing laminate flooring
- The installation must be performed at an ambient temperature of at least the 19 ° C, the surface temperature is 16 ° C at least, and relative humidity from 50% (minimum) and 75% (maximum).
- For optical reasons, the floor planks are sliced vertically of the light source.
- Before installation, should calculate the width of each slice finally: it shall not be less than 5mm. If necessary, the need to cut the first row.