B. Sub-projects Programme northern mountain city - TP. Yen Bai
I. TDA General information:
1. Name of Project: Program northern mountain city - Yen Bai city
2.Ten donors: World Bank
investment 3.Chu: People's Committee of Yen Bai city
4 This total investment: $ 34,230,256, of which:
- ODA: $ 29,450,164;
- contribution: $ 4,780,093
The capital is divided into two phases:
- Phase I (2015-2016) : $ 7,913,471.
Of which: ODA: $ 7,292,922; Contribution: $ 620,549
- Phase II (2017-2021): $ 26,316,785.
Of which: ODA: $ 22,157,242; Contribution: $ 4,159,544
5. Implementation period TDA: From 2015-2020
6. The main content of the project: The project "Urban Program northern mountain - Yen Bai city," according to documents approved plans to invest 18 main categories in the city wards in Yen Bai ; Includes: infrastructure upgrades for 03 low-income area (LIA) at the Hong Ha Ward, Yen Thinh and Nguyen Phuc (LIA 10 small areas); 10. The list of roads and bridges with a total length of 34.2 km (26 routes, 04 small bridges and electricity supply systems, water supply systems in sync with), 01 categories lake embankments; Electric lighting 01danh position on the main streets with a total length of 12.9 km; 01 stream embankments 800m length; 01 categories renovate and expand the kindergarten (06 campuses) and 01 resettlement sites with an area of 4 ha resettlement service for 100 households.
Phase I (2015-2016) Project "Program Northern mountain city - Yen Bai City "will implement 11 construction categories. Items will start in 2015. In it, there are 4 categories completed in 2015 were: Upgrading infrastructure Lia1 area, Lia 3; Quang Trung Street; To Hieu. The remaining items are: Upgrading infrastructure Lia2 area; Ngo Sy Lien; Ha Huy Tap Street; Hoang Van Thu street; Km4 road - Phu Cau documents; Thanh Liem street and road Bun Village will be completed in 2016.
Phase II (2017-2020) is expected to build 37 small items, now investors are organizational design and construction drawing budget of of works under the project.
II. Progress of implementation of investment projects built under the plan
1. For these works have not started construction
1.1 The appraisal and approval of cost estimates
Municipal People's Committee of Yen Bai has actively cooperated with the Department of Planning and Investment to carry out preparatory work invested. Until now completed the design documentation construction drawings and cost estimates for the 11 items of works has approved Phase I (2015-2016).
On 17/04/2015 Yen Bai province issued Decision No. 585 / QD-Committee approving contractor selection plan investment project construction phase I (2015-2016) of 18 Packages (10 XL pack; 03 pack Supervision consultant; 1 pack CF; 1 package DD; 2 pack KT). Based on the selected plan approved contractors. Project Management Committee "urban program mountainous north - Yen Bai City" was organized selection of contractors under the Bidding Law, comply with regulations and the requirements of the PAP.
1.2 Public tendering Categories
* construction package: 10 packages (05 packages were awarded the bid)
Tenders Km4 road - Cau Van Phu, Hoang Van Thu Street, Ha Huy Tap Street, Sugar Bun Hamlet is making and approving bidding documents scheduled Release 10/2015 BD month.
* Package supervision consultants: 03 pack
Currently contractors are supervising the projects under construction and technical assurance, progress and environmental sanitation.
* Packages Other: 05 package includes: Package price evaluation; Package measurement and mapping of land recovery works; insurance contract construction work; Audit works Phase I (2015-2016).
2. For projects under construction
9/2015 In June, the construction package is being implemented: Upgrading infrastructure Lira district 1, Lia3; Upgrading infrastructure Lira district 2; Construction To Hieu; Construction Quang Trung Street; Construction Ngo Sy Lien Street.
The contractors are accelerating construction ensures subscription plan.
3. Implementation progress indicators DLI disbursement.
3.1.DLI 1.1.Ke annual enhancement plan: Decision No 4475 / Committee Chairman dated 22.12.2014 of the city was approved and publicized Committee on the city's Web site.
3.2.DLI 1.2.Bo HR location: Decision No 865 / QD-Committee of the Municipal People's Committee of Yen Bai date 10.04.2015 on strengthening the apparatus with rolling 14/14 The full-time expertise and experience, are tasked to suit each location to ensure the quantity and composition under performing Manual (POM).
3.3.DLI 2.Thuc the investment items Phase I: 11 items of phase I (2015-2016) was registered under the enhanced plan will begin in 2015 and finish in item 4 of 2015, the remaining items completed in 2016. Currently meets the criteria for project eligibility and compliance program fully Action Plan PAP.
3.4.DLI 3.1.Ke asset management plan: PMU has completed status reports assets in preparation for asset management plan approved in accordance with the steps Manual (POM).
3.5.DLI 3.2.Tang annual revenue in place of the city: With the current growth rate is 15 % guaranteed to meet disbursement DLI index 3.2.
4.Tien implementation of the Programme Planning row (PAP).
4.1. PAP 1 - Feedback and database of complaints and denunciations: no single suggestion, legal proceedings and complaints. Municipal People's Committee of Yen Bai with Decision No. 4410 / QD-Committee dated 10.09.2015 on the task, synthesize and report the receipt and settlement of complaints and denunciations, denunciations, feedback and recommendations relating to the program, directly ST, city investigators coordinate with the PMU in direct receipt of private complaints and denunciations, proposals and reflection. PMB has assigned two comrades: Vu Kieu Linh and Nguyen Thanh Hai directly involved PAP1 action.
4.2.PAP 2 - Competitive bidding 07 bid packages were awarded (2 Supervision consultant pack, 5 pack XL). Public procurement comply with procurement laws, rules and regulations in force, applying the terms of the PAP in the bidding. Ensuring competitive bidding rate, 66.6% of Supervision consultant, XL 100%.
4.3.PAP 4 - Valuation of land, site clearance compensation: In the first phase (2015-2016) was only 2 items Hoang Van Thu Ha Huy Tap Street and have done the work of compensation and site clearance (mainly affected soil, garden gates, fences, trees and crops of the people.). To carry out the process of land acquisition, the city People's Committee issued a decision approving the land acquisition plan, survey, measuring, counting the work of land acquisition, land acquisition notice to individual households , land valuation, inventory conducted in the field.
The land acquisition measured by the Bureau of land use rights registration Yen Bai city implementation, site clearance work assigned to Center City Land Development is the specialized're done. Business Property Valuation Valuation Branch and North Vietnamese auction.
Currently Hoang Van Thu route has completed the asset valuation process approved by the provincial People's Committee plans to prepare for compensation and site clearance. Ha Huy Tap route is conducting field inventories, scheduled for completion in May 10/2015 site clearance work.
4.4.PAP 5 - Public consultation: 11 portfolio Phase I (2015-2016) was is the work of public consultations in 2 stage project preparation and project implementation.
Results of consultations 100% of the households attending community consultation has agreed to undertake the project and agreed to donate land, trees and crops and structures within the construction portion.
5.Cong receipt and disbursement of funds
received IDA accounts of the Board are: 3741.0.3023082.92999 be opened at the State Treasury Yen Bai. 2015 projects delivered Yen Bai province in Decision No. 128 / QD-Committee dated 09.02.2015 and the Decision No. 639 / QD-Committee dated 27.4.2015 from development investment from ODA is : 13,000 million. (Of which: 12 090 million from the state budget allocations, 910 million was lent).
Accounts receiving counterpart funds from the budget of the Commission are: 9552 .2.7501169 be opened at the State Treasury of Yen Bai province. 2015 counterpart resources from government bonds to be delivered in Yen Bai People's Committee Decision No. 30 / QD-Committee dated 14/01 / 2015cho project is 7.731 million. Currently disbursed: 8,979trieu copper from IDA fund and 421 million from counterpart funds.
6. Other jobs
- NA