Party B will start the construction right from the day when the A 15.07.2016 or handed in by qualified construction (sanitary premises has been completed, the ceiling and walls finished) option time before and party B receives the deposit, drawings and material samples are the A approval. Total construction schedule for CT1 and building buildings mixed with a time of 90 days.
Party B agrees to hand over on each floor of the A building or each apartment but the minimum total number of apartments Desk delivery of 13 units / time.
If the request from the A that workload increase, the tempo will be adjusted to fit reality. The adjustment will be Party A notice in writing and as a basis for implementing other related provisions of the contract.