* Unit rental of construction machinery and equipment mentioned above is calculated for the time machine working continuously under the guidance of technical staff is 07 hour party A (seven) working hours (called 01 shift ). One month maximum machine operation shall be 26 days (two six days).
In the case of the A to accelerate, the machine must work beyond the time agreed upon, then the cost will be charged as follows :
rental equipment:
(unit rental machine above / 26 days / 07 hours) x Number of extra working time machine.
Money labor: (about 1.50 times the normal workday)
150,000.0 x 1, 5 = 225,000.0 e x number of days of driving a machine do more.