Following the text of the consortium of bidders No. 074 / BĐH-CW3A / 4A dated 05.20.2015; 100 / BĐH-CW3A / 4A dated 25/07/2015 relating to clearance and hand over, so far only the work site was handed over to the consortium of contractors around 2,3Km / 6, 4km (on delivery records) for both Package, while the implementation period of the package has more than 30% since the time the contract commencement date. Moreover, reality in paragraphs (10 segments) were handed over still a lot of problems on compensation of farmers, institutions and lack of width talus ground roadbed caused many difficulties for construction work in the field of Contractors Consortium.
The Consortium Contractor very sympathetic and share the difficulties and problems that you may struggle to board the local settlement. By these actions support you as mobilization Board equipment and construction materials re short against encroachment, in cooperation with local solve many problems, in all this time working on clearance, Contractors Consortium showed a positive spirit of cooperation with you and the local government committee including on financial assistance for the clearance for the common goal is to complete the project as quickly as possible, most effective.
However, the situation at present clearance of the project, the contractor consortium has continued severely affected the mobilization of equipment, personnel and materials to the construction project . To minimize the losses caused to the Contractors Consortium by problems related to the above premises, the Contractor Consortium Board request that your support with local work to provide for the contractor consortium plans clearance and hand over the two CW3A & CW4A Package. Based on clearance plan, we will update the detailed action plan for the remaining period of the Project Board to send you, in order to create favorable conditions for the parties to coordinate their work efficiency, meet the overall progress of the project.
đang được dịch, vui lòng đợi..