NOTES: FOR JOOP HARMS VISIT 14 September to 03 October 2014BackgroundC dịch - NOTES: FOR JOOP HARMS VISIT 14 September to 03 October 2014BackgroundC Anh làm thế nào để nói

NOTES: FOR JOOP HARMS VISIT 14 Sept

NOTES: FOR JOOP HARMS VISIT
14 September to 03 October 2014

Background
CS7 Operation and Maintenance Management Contract
5 Tasks
• Roll out Caretaker Concept
• O&M Management support to new OCC
• NRW Reduction and Management
• Implementation of Improved Distribution Practices
• Training Programs

23 Deliverables overall in project. 4 link to Asset Management
• D7 Strategy for Asset Management and NRW reduction
• D10 Detailed list of pipelines for upgrading/replacement
• D12 Cause and Remedies of poor state distribution networks
• D13 Design manual for tertiary distribution

Objectives
1 D10 Can we using:
• Local knowledge
• Existing information
• Leak Repair databases
• PRP methodology
Gain enough information for the preparation of D10 and introduce PRP as a system in 5 distribution companies or at least a local system based on PRP
2 D12 Can we using:
• Expert Knowledge
• Existing information
• Leak repair databases
• PRP methodology
Gain enough information for preparation of D12

3 Detailed Leak Detection and Repair Analysis
• Leak detection records and reports
• Leak registering records and reports
• Leak repair records and reports
• ALR – AWARE LOCATE REPAIR
• Link in areas where excavation permits are held up
• Link the above to NRW

Tools
• 5 distribution companies and working teams
• Leak repair databases
• Leak detection reports
• Leak repair reports
• ALR
• PRP Methodology

0/5000
Từ: -
Sang: -
Kết quả (Anh) 1: [Sao chép]
Sao chép!
NOTES: FOR JOOP HARMS VISIT
14 September to 03 October 2014

Background
CS7 Operation and Maintenance Management Contract
5 Tasks
• Roll out Caretaker Concept
• O & M Management support to new OCC
• NRW Reduction and Management
• Implementation of Improved Distribution Practices
• Training Programs

23 overall Deliverables in project. 4 link to Asset Management
• D7 Strategy for Asset Management and NRW reduction
• D10 Detailed list of pipelines for upgrading/replacement
• D12 Cause and Remedies of poor state distribution networks
• D13 Design manual for tertiary distribution

Objectives
1 D10 Can we using:
• Local knowledge
• Existing information
• Leak Repair databases
• PRP methodology
Gain enough information for the preparation of D10 and introduce PRP as a system in 5 distribution companies or at least a local system based on PRP
2 D12 Can we using:
• Expert Knowledge
• Existing information
• Leak repair databases
• PRP methodology
Gain enough information for preparation of D12

3 Detailed Leak Detection and Repair Analysis
• Leak detection records and reports
• Leak registering records and reports
• Leak repair records and reports
• ALR-AWARE LOCATE REPAIR
• Link in areas where excavation permits are held up
• Link the above to NRW


Tools • 5 distribution companies and working teams
• Leak repair databases
• Leak detection reports
• Leak repair reports
• ALR
• PRP Methodology

đang được dịch, vui lòng đợi..
Kết quả (Anh) 2:[Sao chép]
Sao chép!
NOTES: FOR JOOP HARMS VISIT
14 September to 03 October 2014

Background
CS7 Operation and Maintenance Management Contract
5 Tasks
• Roll out Caretaker Concept
• O&M Management support to new OCC
• NRW Reduction and Management
• Implementation of Improved Distribution Practices
• Training Programs

23 Deliverables overall in project. 4 link to Asset Management
• D7 Strategy for Asset Management and NRW reduction
• D10 Detailed list of pipelines for upgrading/replacement
• D12 Cause and Remedies of poor state distribution networks
• D13 Design manual for tertiary distribution

Objectives
1 D10 Can we using:
• Local knowledge
• Existing information
• Leak Repair databases
• PRP methodology
Gain enough information for the preparation of D10 and introduce PRP as a system in 5 distribution companies or at least a local system based on PRP
2 D12 Can we using:
• Expert Knowledge
• Existing information
• Leak repair databases
• PRP methodology
Gain enough information for preparation of D12

3 Detailed Leak Detection and Repair Analysis
• Leak detection records and reports
• Leak registering records and reports
• Leak repair records and reports
• ALR – AWARE LOCATE REPAIR
• Link in areas where excavation permits are held up
• Link the above to NRW

Tools
• 5 distribution companies and working teams
• Leak repair databases
• Leak detection reports
• Leak repair reports
• ALR
• PRP Methodology

đang được dịch, vui lòng đợi..
 
Các ngôn ngữ khác
Hỗ trợ công cụ dịch thuật: Albania, Amharic, Anh, Armenia, Azerbaijan, Ba Lan, Ba Tư, Bantu, Basque, Belarus, Bengal, Bosnia, Bulgaria, Bồ Đào Nha, Catalan, Cebuano, Chichewa, Corsi, Creole (Haiti), Croatia, Do Thái, Estonia, Filipino, Frisia, Gael Scotland, Galicia, George, Gujarat, Hausa, Hawaii, Hindi, Hmong, Hungary, Hy Lạp, Hà Lan, Hà Lan (Nam Phi), Hàn, Iceland, Igbo, Ireland, Java, Kannada, Kazakh, Khmer, Kinyarwanda, Klingon, Kurd, Kyrgyz, Latinh, Latvia, Litva, Luxembourg, Lào, Macedonia, Malagasy, Malayalam, Malta, Maori, Marathi, Myanmar, Mã Lai, Mông Cổ, Na Uy, Nepal, Nga, Nhật, Odia (Oriya), Pashto, Pháp, Phát hiện ngôn ngữ, Phần Lan, Punjab, Quốc tế ngữ, Rumani, Samoa, Serbia, Sesotho, Shona, Sindhi, Sinhala, Slovak, Slovenia, Somali, Sunda, Swahili, Séc, Tajik, Tamil, Tatar, Telugu, Thái, Thổ Nhĩ Kỳ, Thụy Điển, Tiếng Indonesia, Tiếng Ý, Trung, Trung (Phồn thể), Turkmen, Tây Ban Nha, Ukraina, Urdu, Uyghur, Uzbek, Việt, Xứ Wales, Yiddish, Yoruba, Zulu, Đan Mạch, Đức, Ả Rập, dịch ngôn ngữ.