STATUS:
1. The project site of Antenna can be powered from two lines are:
- 35kV line behind the company, the distance from the last electric pole fence 83 meters cun way;
- 22kV Line run through the entire front surface of the Company, a fence 0.5 meters.
These two lines are fed from the station 110kV Dong Van. Technically, all ensure reliability and stability alike.
On the provincial People's Committee has committed power supply to the fence of the company, the current PPC has performed as committed, because Around The company has generated 2 high voltage lines outside the fence. So more power poles planted as proposed by the company was not justified.