Both sides understand the delay time of the erection of the tower crane at the head P9 is caused by the work plan approved by the tower crane, tower crane foundation of Consulting and Investor Package rigorous J1. And would not blame any party during the construction cranes, but not placed in erection is possible. J1 Steering Committee is responsible, do not let any construction work on the construction site damage to the details gathered tower cranes currently on the construction site.