FORCE MAJEURE5.1. unforeseen events are events that happen brings objectivity and is beyond the control of the party, such as an earthquake, hurricane, flood, Tornado, flood, tsunami, landslides; a fire; war or danger of war ... and other disasters have not been exhausted, the measurement of the change of policy or prohibit the competent authorities of Vietnam ...-The one side does not fulfill its obligations due to force majeure events shall not be the basis for the other party to terminate the contract and claim damages. However the party affected by force majeure events are supposed to:+ Conduct measures to prevent rational and necessary alternative measures to minimize the influence due to unforeseen events cause.+ Notify other party of unforeseen events occurring within 7 days right after the event.5.2. In case of unforeseen events occur and cause damage to the material, human, then the 2 parties will not be liable for the binding associated with the contracting economy.