Article 45. Check energized condition connection point
1. Customers wishing to connect with responsibility agreement with the power transmission unit test execution day reality at the connection point.
2. Power transmission unit is responsible for coordinating with unit power system operation and power market agreements with customers wishing to connect the self-test records, test records and reality set connection points.
3. Where the power transmission unit notify connection points or equipment related to the connection points of customer connection needs unqualified energized, customers wishing to connect to calibrate and supplement or replace equipment as required and agreed upon with the power transmission unit of time examined later.
4. Power transmission unit and operating unit power system and electricity market must be signed with customers wishing to connect inspection record closing conditions electrical connection points.