2.3. Installation works:
- The landfill was made after the underground structures was accepted and allowed subsequent construction work. Landfill construction machines combined with crafts. The land is filled with periods and compacted by compactor toads reach design density.
- The land is divided into foundation fill from 20-25cm thick layers, compacted by compactor toads reach design density, combined dress craft in from the edges.
- the landfill outside is done after construction is complete earthing system, technical and underground pipes.