On 03/03/205 the contractor signed a handover of premises (justice process from km 14 + 310.19-:-km14 + 489), but in reality, on 18/03/2015 managing new Railings bridge bus finished dismantling the existing buildings in order to hand over the premises to the contractor. With time delivery as above, the contractor will not be able to cast the pile, used for the pile to try on 28/03/2015 as the progress. Through learn in Hai Phong city, contractors found a concrete company, and XD Haiphong, have produced the kind of stakes, meet the technical requirements of the project. To ensure the progress of the project, the contractor proposed to buy stakes due to concrete and joint stock company Hai XD manufacture, used as a peg to try.
đang được dịch, vui lòng đợi..