EXECUTION MEASURES
To: BLD Co. TEBODIN.
- Project: Residence Hempel factory - Long Thanh.
- Package: Process & HVAC exhaust.
- Construction unit: Phuc Khang Binh Co., Ltd.
1. Purpose.
The purpose of this construction method is to describe the process of construction and installation of equipment inside the building on the basis of conformity with technical standards stipulated in the contract included design drawings and regulations safety regulations by the company Tebodin poses.
2. Scope of work.
The scope of work is concrete chimney installation, vacuum pipe connection on the ceiling inside the room and Ventilation.
3. Construction methodology.
- Preparing materials and equipment: Chimney, wind pipe, welding machines, cutters, drills, bolts + canopy, silicon, of seals, power cord, buckles, embroidery Crane ...... ....................................................... ...........................................
- Implementation: After fully prepared to carry supplies and equipment operating and installation follow these steps.
step 1: Insert the original paragraph alignment and chimney inside the room to the selected location.
step 2: Insert the two remaining sections of the chimneys into one another, the anchor cable mounting positions available on the chimney, the three strands connected together to make hook placement, use the crane to lift and place the chimney on the original piece was mounted position before. Try the chimney with flange bolts, anchor cable and chimney.
Step 3: Use a duct for connection between fans, recovery systems and flue dust.
- Completion and testing: Report consulting representative director surveys to check after the work is completed.
4. Safety measures.
The safety regulations must be applied to all construction workers on the construction site as below.
- Fully equipped labor protection, ensure implementation of regulations when working on high welding and cutting process.