Subject: Overcoming erosion at A2 abutment of Bailey bridge, Tam An TMC, package 8. Dear Sirs,Reference is made to CSC's letter No. LPk8CHD-16-144 dated April 26, 2016 regarding the above captioned subject.We would like to report the progress of repairing at A2 abutment of Bailey bridge, Tam An TMC, package of 8 on the afternoon of April 26, 2016 as follows:2.1. Already filling the uncovered section of intercepting ditch for water restraining from high water and lower section flowing into the abutment A2.2.2. Already backfilling the erosive ditch (at the water flowing position) by sand to the same level with intercepting ditch.(Please attached photos).We highly appreciate your approval and the issue of "work recover order" so that we can proceed to the next work.Thanks for your cooperation!Yours Sincerely,