Package CW2C contractor constructing the road are within intersection QL80 highway with 80. Through the profile research technical design of the project and the existing drainage and we see a number of issues as follows:1. In the logical process Km1 + 46.71 branch LSR-R3: in this position the horizontal box drain existing lines. According to the technical design will expand the road over both positions. However in the designed modern technique extension in the street rather than have expanded existing drain design.2. In the logical process Km0 + 858.19 branch LSR: this location has existing service to track the irrigation of agricultural land. However, technical design, not the sewer layout at this location.To ensure meet the technical requirements and the requirements of local agricultural production, the contractor submitted the investor considering comments directed to the Contractor made.