1.2 THE FIELD DEVELOPMENT PLAN
second strategic mistake is a mistake on the field development plan. VSP did not have a long-term development planning, technological diagrams 5 year average is calibrated once. Consequently, marine works together built more practical needs, while a series of works in the short term, only effective for a short time and then be transferred to the reserve. Typically, hundreds of kilometers of underground piping is currently vacant, small compressor rig - works that could stop right there without influence on mining technology, the MSP by the survival of the majority of equipment is meaningless, it must be realized whether this works is meaningless in terms of technology but VSP must continue to pay for the maintenance staff to operate, repair and clean-up bill later.
Consequently, more effective marine works needed, no need really and completely unnecessary was built. The burden of the cost of maintaining the operation of this project is enormous that VSP will suffer until the brave removed them.
(the writer of this article has been e / c, First Deputy General Director Badikov and e / c director of a hit on meeting XN threatened for opposing the construction of 2 km pipeline insulated "worth about $ 1.5 million, the pipeline is 1 year after the operation is stopped and perhaps never work again)
should be aware that in a lifetime of marine works, construction costs are only 20% - 25% of the total cost, 75% - 80% is the cost to maintain operations and revenues clean. For example, the cost of 25 million USD to build MSP (excluding the value of wells), maintenance costs for 20 years is $ 110 million. for Mekong mine construction cost is 297 million mines, operating cost is 976 million.
đang được dịch, vui lòng đợi..