Based on the minutes handed the premises (from justified the Km 17 + 300-:-miles 17 + 600), 12-05-2015 of the owner, the contractor undertook to plug GPMB boundary piles, to determine the scope of construction for the projects. Contractors completed work on cleaning up a construction glowing in 50.50 m (fifty half meters) that the owner has delivered, with the width of the ground delivery as above, the contractor will not be able to perform trials and proceed to the next task because the console scope by lack of breadth than the profile design drawing (attachment survey and drawing of horizontal spindles Km17 + 300 and 400 + Km18). The contractor has invited representatives of the owner, TVGS, sets the scene to confirm the incident mentioned above.