Based on the groundbreaking command on 08/06/2015 contractors (CC1) conducted the work in progress aside, in the construction process has a number of units for construction contractors work section ago to disruptive and prevents the contractor (CC1), however the contractor (CC1) has combined the parties concerned solving the problems mentioned above. But on June 12, 2015 contractors (CC1) getting text from Tam Thanh Hung said of the dispute between construction materials company Saint-Gobain North Vietnam with the contractors had done previous work section and at the suggestion of Tam Thanh Hung with construction materials company Saint-Gobain North Vietnam about the process of the dispute mentioned above , to the contractor (CC1) can deploy the next job. Dear investor proposals, supervising, soon solve the dispute so as not to affect the overall progress of the project.